Construction Technology of LVT Floor part 1 and 2
(1) Grass-roots treatment
1. After the installation of walls, roofs, doors and windows, clean up the ground debris.
2. Clean up sand, oil and residues on the surface of the grass-roots.
3. Clean up the dust and sand on the ground.
4. After the floor is thoroughly cleaned, the interface agent should be rolled and coated uniformly.
(2) Self-leveling Construction
1. Check whether the cement self-leveling meets the relevant technical standards, such as expired self-leveling shall not be used.
2. Pour proper amount of self-leveling into the dissolver and dilute it with clean water according to the product description.
3. Stir well until the cement is self-leveling into a fluid.
4. Sequentially, self-leveling is inverted on the construction ground, scraped flat with rake-tooth scraper, and the thickness is about 2-3 mm.
5. Pedestrians and articles shall not be piled up within 4 hours after the completion of self-leveling construction.
(3)Relevant tools
1. Floor treatment: surface humidity tester, surface hardness tester, floor grinder, high-power industrial vacuum cleaner, wool drum, self-leveling mixer, 30-liter self-leveling mixing barrel, self-leveling tooth scraper, nail shoes, self-leveling exhaust cylinder.
2. Floor laying: floor trimmer, cutter, two-meter steel ruler, glue wiper, steel press roll, slotting machine, welding gun, month-shaped cutter, welding rod trimmer, combined marker.