PVC floor in the modern office decoration, used very common, with water, fire and so on. PVC flooring in the office decoration of the laying of the steps are as follows:
1, the mixing of self-leveling slurry poured on the construction of the floor, it will flow on its own and leveling the ground, if the design thickness of ≤ 4 mm, you need to use a special scratch scraper scraping slightly.
2, then allow the construction staff to wear special spikes, into the construction ground, with a dedicated self-leveling deflation roller gently rolling self-leveling surface, the air mixing in the air release, to avoid the bubble surface and interface height difference.
3, Please close the site immediately after construction, prohibit walking within 5 hours, avoid heavy impact within 10 hours and lay PVC floor after 24 hours.
4, winter construction, laying of the floor should be self-leveling construction after 48-72 hours.
5, for the self leveling leveling polishing, should be self-leveling cement completely dry after.