1. After the artificial turf of the football field is laid, the joints are left with the corresponding number of centimeters and the joint cloth is coated and glued. When applying glue and bonding, it is necessary to control the temperature and the contact time with air (not too long).
2. When the roller is pressed, the artificial turf of the football field is in full contact with the ground and the rolling direction is the same, and it is not possible to repeatedly crush.
3. It is necessary to check the flatness of the artificial grass floor, whether there is a bulge at the joint, and whether the joint is bonded together.
4. Fill the quartz sand and rubber particles, fill the quartz sand into the artificial turf, comb the straw with a carding machine, if it is not combed, use the artificial combing grass to ensure that the quartz sand is filled flat and fill the rubber granules in the same way. . The injection of quartz sand and rubber particles can make the grass erect and increase the comfort of the athlete.
5. Check the site construction and carry out on-site garbage disposal.
6. Materials and construction accessories should be tested during construction. In the case of a sufficient number of technicians in the construction of the football field, it is necessary to ensure adequate supplies. Of course, we must pay attention to the safety of construction. The site avoids the phenomenon of open flames and leakage of electricity, and avoids construction in rainy and foggy days to ensure that the synthetic grass lawn construction of the football field is completed within the specified time.